|
Environmental
Division
Air Quality Monitoring
Programme - CAMP DATA
CAMP - Phase III
Monitoring of ambient air quality using automated
systems
Scope:
Recognizing the
growing problem of air pollution and the importance of having a proper air
quality monitoring system in the Colombo Urban area, World Bank mission in 1992
on the “Colombo Urban Transport Project” (CUTP) incorporated this monitoring
programme as a tool for a proper air pollution management programme in Colombo
with the objective of reducing air pollution in Colombo by year 2000.
Introduction:
Under this programme
two fixed and one mobile air quality and meteorological monitoring stations
were commissioned in December 1996. Each unit could measure ambient SO2,
NO, NO2, NOx, CO, O3, PM-10 levels and the meteorological
parameters such as Wind Direction (WD), Wind Speed (WS), Vertical Wind Speed
(VWS), Solar Radiation (SR), Ambient Temperature (ATE) and Precipitation (RF),
continuously.
In compliance with the recommendation of the
World Bank and the “Clean Air 2000” Action Plan Committee, this monitoring
programme was executed by the Environmental Division of NBRO for the
Central Environmental Authority (CEA).
FIXED STATION - MONITORING PROGRAMME
One of the fixed stations is
located in front of the Fort Railway Station which functions as a peak air
pollution monitoring station with respect to transport and the other fixed
station is located at the premises Department of Metrology, Bauddhaloka Mawatha,
Colombo – 07, functioning as a background air pollution monitoring station in
Colombo City.
The data of these two monitoring stations are being sent to the Central
Environmental Authority of Sri Lanka, weekly and monthly basis to disseminate
to the public and also to make use of for regulatory activities.
MOBILE STATION - MONITORING PROGRAMME
The mobile laboratory was first
used to crosscheck two fixed stations during the period April 1997 – May
1997. Since then the Mobile Air Quality
Monitoring Laboratory has been utilized for the following activities.
| Month |
Location |
Duration |
Client |
| August 1997 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) Ltd. |
| October 1997 |
Maskeliya |
03 days |
Central Environmental Authority |
| December 1997 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) Ltd. |
| January 1998 |
-do-
|
-do-
|
-do-
|
| February 1998 |
Kerawalapitiya |
-do- |
JICA |
| March 1998 |
Sapugaskanda |
-do- |
Asia Power (Pvt.) Ltd. |
| April 1998 |
University of Peradeniya |
02 days |
International Work Shop on Acid rain - Commonwealth Science Council Programme
|
| June 1998 |
Kerawalapitiya |
Two weeks |
JICA |
| August 1998 |
Sapugaskanda |
-do-
| Unilever Ceylon Limited. |
| Sapugaskanda |
One month |
Central Environmental Authority |
| October 1998 |
Kollupitiya |
Two Days |
Central Environmental Authority |
| Paliyagoda |
Two days |
| Maradana |
Two days |
| Nov/Dec |
Sapugaskanda |
Two
weeks | Asia Power (Pvt.) Ltd. |
| February 1999 |
Paliyagoda |
One week |
ERM Lanka (Pvt.) Ltd. |
| March 1999 |
Hambantota |
One week |
-do- |
| April 1999 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) Ltd. |
| May 1999 |
Anuradapura |
One week |
Central Environmental Authority |
| June 1999 |
Puttam |
-do-
|
-do-
|
| June 1999 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) Ltd. |
| Kandy |
One week |
Central Environmental Authority |
| July 1999 |
Nuwara Eliya |
-do-
|
-do-
|
| Hambantota |
-do-
|
-do-
|
| September 1999 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) Ltd. |
| February 2000 |
Sapugaskanda |
Two weeks |
Asia Power (Pvt.) ltd. |
Out of these activities,
monitoring of background air pollution at Hambantota, Kandy, Nuwara Eliya,
Anuradhapura, Puttalam were carried out as a “Air Pollution Monitoring – Islandwide Programme” as per the recommendation made by the sub committee on
air pollution monitoring under the “Clean Air 2000” action plan.
The locations were selected to
represent the background air quality within the area.
Site Description :
| Location |
Land use |
Landscape
Topography |
| Hambantota |
Meteorological Station |
Flat terrain |
| Anuradapura |
Meteorological Station |
Flat terrain |
| Puttalum |
Meteorological Station |
Flat terrain |
| Kandy |
Meteorological Station |
Hilly area |
| Nuwara Eliya |
Radio Transmission Station |
Hilly area |
Monitoring of Galle, Kalutara,
Negambo and Kurunagela were carried out to see the urban pollution in those
areas due to the mobile sources. This programme was carried out as per the
instructions made by the Presidential Task force through Ministry of Forestry and
Environment.
Site Discription :
| Location |
Land use |
Landscape Topography |
Wind Direction |
| Galle |
Government School | Flat terrain |
South - West |
| Kalutara |
Public play ground | Flat terrain |
South - West |
| Kurunegala |
Public play ground | Flat terrain |
North - East |
| Negambo |
Public play ground | Flat terrain |
North - East |

Back |